中国石油勘探 ›› 2020, Vol. 25 ›› Issue (2): 96-109.DOI: 10.3969/j.issn.1672-7703.2020.02.010

• 工程技术 • 上一篇    下一篇

钻井优化系统在国内非常规油气资源开发中的实践

张福祥1 ,郑新权2 ,李志斌1 , 陈建林3 ,李庆3 ,路宗羽3 ,龚翔旻1 ,曹新予1   

  1. 1 海峡能源股份有限公司;2 中国石油勘探与生产分公司;3 中国石油新疆油田公司
  • 出版日期:2020-03-15 发布日期:2020-03-13
  • 基金资助:
     

Practice of drilling optimization systems in the development of unconventional oil and gas resources in China

Zhang Fuxiang1, Zeng Xinquan2, Li Zhibin1, Chen Jianlin3, Li Qing3, Lu Zongyu3, Gong Xiangmin1, Cao Xinyu1,   

  1. 1 Strait Energy Ltd; 2 PetroChina Xinjiang Oilfield Company; 3 PetroChina Exploration and Production Company
  • Online:2020-03-15 Published:2020-03-13
  • Supported by:
     

摘要: 相对于北美,国内非常规油气资源勘探开发起步较晚。页岩气勘探开发始于“十二五”初,致密油、致密气、 页岩油勘探开发则始于“十三五”初,但在“十三五”期间得到了快速发展,特别是川渝页岩气藏、准噶尔盆地玛湖 砾岩油藏、吉木萨尔页岩油藏已进入规模开发阶段,成为中国石油“十三五”末及“十四五”期间天然气和原油上产 的最重要领域。与常规油气资源相比,非常规油气资源储层条件差,需要大规模“水平井+ 体积压裂”才能实现有 效开发。然而,由于受钻机装备条件和水平井钻井工具性能,特别是理念和方法的限制,国内非常规水平井普遍存在 钻井效率低、建井周期长的问题:一般垂深2000~3000m、水平段1500~2000m 的水平井钻井周期为60~90 天。而 北美钻一口水平井基本都能控制在15~25 天:一般垂深2000~3000m、水平段长2000~3000m。国内一部钻机一 年只能钻2~3 口水平井,而在北美一部钻机一年能完成15~20 口水平井。随着国内非常规油气资源的规模开发,钻 机紧缺的矛盾日益突出,钻井效率已经成为严重制约国内非常规油气资源快速规模上产的瓶颈问题。北美大幅度提高水平井钻井效率的原因有管理和技术两大因素,其中技术主要表现在以下5 个方面:一是钻机配 套能力的不断升级;二是井下工具可靠性和稳定性的提升;三是大平台工厂化作业;四是远程实时支持与决策系统; 五是系统优化钻井理念和方法的应用。2018 年海峡能源股份有限公司与美国K&M 钻井工程咨询公司合作,引进国 际先进的系统优化钻井理念和方法,率先在川渝地区长宁页岩气藏和新疆玛湖砾岩油田开展了水平井钻井提速先导性 试验,大幅缩短了建井周期,验证了系统优化钻井方法在国内非常规油气资源开发中的可行性。为了达到进一步推广 的目的,2019 年在玛湖砾岩油田开展区块提速试验,同样取得了显著的提速效果,进一步证明了系统优化提速理念 和方法具有科学性、广普性和可复制性,是经验钻井向科学钻井迈进的重要实践,展示出了非常广阔的推广应用前景。

 

关键词: 非常规油气资源, 页岩革命, 系统优化钻井, 建井成本

Abstract: Compared with North America, the exploration and development of unconventional oil and gas resources in China began relatively late. Shale gas exploration and development started at the beginning of the “12th Five Year Plan” period. The exploration and development of tight oil, tight gas and shale oil started at the beginning of the “13th Five Year Plan”, and developed rapidly during the “13th Five Year Plan” period. In particular, development of shale gas in Sichuan and Chongqing, conglomerate oil field in the Mahu sag, and shale oil reservoir in the Jimsar sag in the Junggar Basin, have entered the stage of large-scale development, becoming the most important field for oil and gas production increase at the end of the “13th Five Year Plan” and into the period of the “14th Five Year Plan” of CNPC. Compared with conventional oil and gas, unconventional oil and gas resources have poor reservoir conditions, which require large-scale “horizontal well + volume fracturing” to achieve effective development. However, due to limitations of rig equipment and performance of horizontal well drilling tools, and especially shortcomings in concepts and methods, issues of low drilling efficiency and long well construction periods are common in unconventional horizontal wells in China. Generally, the drilling period of a horizontal well is 60-90 days, with a vertical depth of 2,000-3,000 m and a horizontal section of 1,500-2,000 m. In North America, the drilling period of a horizontal well can basically be controlled within 15-25 days, with a vertical depth of 2,000- 3,000 m and a horizontal section length of 2,000-3,000 m. A drilling rig in China can only drill 2-3 horizontal wells a year, while in North America a drilling rig can complete 15-20 horizontal wells a year. With the large-scale development of unconventional oil and gas resources in China, the challenge of drilling rig shortage is increasing. Drilling efficiency has become a bottleneck problem which seriously restricts the rapid and large-scale production of unconventional oil and gas resources in China. There are two advantages which support the great improvement of drilling efficiency of horizontal wells in North America: management and technology. In technology, there are five main aspects: the first is the continuous upgrading of supporting capacity of drilling rig; the second is improvement of the reliability and stability of downhole tools; the third is large-platform factory operation; the fourth is remote real-time support and decision-making systems, and the fifth is the application of the concepts and methods of systematic drilling optimization. In 2018, Strait Energy cooperated with K&M drilling engineering consulting company of the United States to introduce internationally-advanced concepts and methods for systematic drilling optimization. Pilot testing of drilling speed increase in horizontal wells was first carried out by Changning Shale Gas Co., Ltd. in the Sichuan and Chongqing area, and in the conglomerate oil field in the Mahu sag in Xinjiang, which greatly shortened the well construction period and verified the feasibility of systematic drilling optimization methods in the development of unconventional oil and gas resources in China. In order to further promote this, testing of speed increase in the whole block was carried out in the conglomerate oil field in the Mahu sag in 2019, which also achieved remarkable results. This further proves that the concepts and methods of systematic optimized drilling speed increase are scientific, universal and replicable, which is an important shift in practice from experience-based drilling to scientific drilling, and shows very promising prospects for popularization and general application.

中图分类号: